Owasso is advancing plans to widen and add traffic signals at E. 86th St. N. and N. 161st E. Ave., with construction estimated at $4.3 million. That figure does not represent the project’s total cost.
The Public Works Department shared the proposed improvements in a Nov. 23, 2026, announcement, linking to a project presentation describing the design, utility work and land needed.
The intersection project was selected from Owasso’s 2013 Transportation Master Plan. The presentation identifies the city’s sales-tax-supported Capital Improvement Fund as its funding source.
Proposed improvements
Plans call for a wider intersection with traffic signals, center left-turn lanes, concrete pavement and an underground stormwater system.
Along the west leg of 86th Street, the proposed design includes an 8-foot shared-use path on one side and a 5-foot sidewalk on the other.
The presentation names Dwayne Henderson as city engineer and Kimley-Horn’s Rusty Akerman as project manager. It assigns the city full responsibility for engineering, right-of-way acquisition, utility relocation and construction costs, while listing $4.3 million specifically as the construction estimate.
Design and property acquisition
A status report included in the Oct. 27, 2026, Owasso Capital Improvement Committee meeting packet put engineering design at 80% complete. It also reported that a right-of-way acquisition agent had been hired, with work to obtain property rights and easements expected to begin in October.
The Sept. 1 City Council agenda packet included staff’s recommendation for an agreement with Tulsa-based Universal Field Services, capped at $71,800. That amount covers acquisition-related services, including appraisals, title work and assistance securing right-of-way and easements—not the purchase price of the land.
Maps in the project presentation show proposed property needs around the intersection, including parcels near Cambridge Park.
Utility changes
The plans call for Rogers County Rural Water District No. 3 to move several water lines and valves. Oklahoma Natural Gas would relocate infrastructure into an easement south of 86th Street, while AT&T, Cox and Verdigris Valley Electric Cooperative would make relocations as needed.
AEP would build new lines for a new subdivision that accommodate the intersection improvements.
Residents seeking more information can contact Henderson at (918) 272-4959 or [email protected].