Broken Arrow's City Council unanimously approved the sale of more than $26 million in general obligation bonds. Two of the three series mark the first sales under the $415 million bond package voters approved in April, while the third is the ninth series from the 2018 bond election.

Robert W. Baird won all three series as the lowest-interest-rate bidder, according to the city's announcement.

Jon Wolff, president and chief compliance officer of Municipal Finance Services, Inc. in Edmond, facilitated the sale. The city received four bids for each series by the 11 a.m. deadline on Nov. 3. The council had authorized the solicitation of bids in October.

Series 2026B, valued at $14,750,000, marks the first sale under the voter-approved 2026 bond authorization. Robert W. Baird's winning bid carried a 4.1337 percent interest rate.

Wolff told the city that the Series 2026B sale was "technically the first sale under the election authorization of the $415 million …" and noted that Robert W. Baird is "a very aggressive bidder for Oklahoma bonds."

Series 2026A, the ninth series sold under the 2018 bond election, went to Robert W. Baird at 4.1402 percent. Series 2026C, a $2 million sale, will fund a $1,156,000 stormwater project and $844,000 in drainage projects. Robert W. Baird's winning bid on that series was 4.2155 percent.

"We've seen the markets fluctuate up and down the last week, and that continued through this morning," Wolff said. "The City came in positively based on where the market has been in the last month."

Broken Arrow voters approved the $415 million Build our Future BA general obligation bond package on April 7. Seven propositions passed, with stormwater earning 75 percent approval and quality of life and public facilities each receiving 66 percent. The city said at the time of the election that the current millage rate for property taxes was expected to remain the same.

The bonds will be funded in December.